Construction of hamams

Our company carries out the construction of hamamson a turn-key basis in Moscow and the Moscow region.

tel. +7 985 411 - 12 - 12

Hammams are designed in two main stages that are preparatory and construction work.
At the first stage, measurements and consultations are carried out (1 to 2 working days), elaboration of internal layout options (1 to 2 working days), designing (3 to 5 working days), purchase of necessary equipment and materials (about 4 days). During the second stage, the construction of a frame structure is underway (15 to 20 days), the purchase of materials for interior decoration (7 to 14 days), finishing works (10 to 14 days).